Area Construction Activities , con't
Improvements to the Richey Park drainage system are moving forward as expected along 13th Avenue from Everett Court to Garrison. Beginning on Monday, July 19 Garrison will close for crews to cross the pipe under the roadway. This closure will be in place for approximately two weeks and current scheduling indicates that Garrison will reopen the night of Friday, July 30, 2010.
The underground drainage improvements along 13th Avenue between Zephyr and Carr are very near completion, as crews complete final connections to existing pipes.
The concrete deck on the light rail bridge over Wadsworth is now in place. Work on this bridge continues as crews work on the concrete platform of the station on top of the bridge. The remaining RTD acquired property at 14th and Wadsworth will be taken down later this month, completing the demolition activities in this area.